新房装修流程
1、前期设计(设计定稿后同步跟物业申请装修许可):
1. The early design (after the design is finalized, with the property application decoration license):
主要是根据自己的生活习惯设计,并且对自己的房间进行一次详细的测量,小伙伴们不要犯懒,最好亲自测量一遍,测量的内容主要包括:明确装修过程涉及的面积。特别是贴砖面积、墙面漆面积、壁纸面积、地板面积;明确主要墙面尺寸。特别是以后需要设计摆放家具的墙面尺寸。
It is mainly based on their own habits and designs, and makes a detailed measurement of their rooms. Do not commit laziness, and better measure them in person. The contents of the survey include: making clear the area involved in the decoration process. Especially the tiling area, area of wall paint, wallpaper area, floor area; clear main metope size. In particular, it is necessary to design the wall size of the furniture in the future.
2、主体拆改(同步报装天然气):
2. The main body dismantling and modification (synchronized natural gas):
进入到施工阶段,主体拆改是最先上的一个项目,主要包括拆墙、砌墙、铲墙皮、拆暖气、换塑钢窗等等。主体拆改说白了,就是先把工地的框架先搭起来。
Enter the stage of construction, the main Chaigai is first on a project, mainly including wall, wall, shovel, and heating, for plastic steel windows and so on. The main body of the reform is white, that is, first to build the construction site of the first frame.
3、水电改造(同步申请天然气埋管):
3. Hydropower transformation (in synchronous application for natural gas buried pipes):
水电路改造之前,主体结构拆改应该基本完成了。在水电改造和主体拆改这两个环节之间,一些小伙伴可能知道,还应该进行橱柜的第一次测量。其实所谓的橱柜第一次测量并没有什么实际内容,因为墙面和地面都没有处理,橱柜设计师不可能给出具体的设计尺寸,而只是就开发商预留的上水口、油烟机插座的位置,提出一些相关建议。
Before the reform of the water circuit, the main structure should be basically completed. Between the two links of the hydropower transformation and the main dismantling, some small partners may know that the first measurement of the cabinet should also be carried out. In fact, the so-called cabinet for the first time to measure and not what the actual content, because no metope and ground treatment, cabinet designer can not give a specific design size, and just the upper nozzle, lampblack machine socket developers reserved position, put forward some relevant suggestions.
4、泥瓦:
4, mud tile:
瓦工作业的过程,涉及以下三个环节的安装:过门石、大理石窗台的安装。过门石的安装可以和铺地砖一起完成,也可以在铺地砖之后,大理石窗台的安装一般在窗套做好之后,安装大理石的工人会准备玻璃胶,顺手就把大理石和窗套用玻璃胶封住了。地漏的安装。地漏是家装五金件中第一个出场的,因为它要和地砖共同配合安装。
The process of bricklaying operations, involving the following three aspects: the installation of door stone, marble windowsill installation. The door of the stone floor tile installation can be completed together, also can be in the tile, marble windowsill installation General in the window after installation completes, marble workers will be ready to glass glue, smoothly put the marble and the window glass glue is sealed. The installation of ground leakage. The floor drain is the first appearance in the home hardware, because it needs to be fitted together with the floor tiles.
5、木工:
5. Carpenter:
瓦工、木工、油工是施工环节的“三兄弟”,基本出场顺序是:瓦木油。原则是“谁脏谁先上”也是决定家装顺序的一个基本原则之一,其实像包立管、做装饰吊顶、贴石膏线之类的木工活从某种意义上说也可以作为主体拆改的一个细环节考虑,本身和水电路改造并不冲突,有时候还需要一些配合及提前考虑到。
Bricklaying, carpentry, oil and construction workers are part of the "three brothers", the basic order of appearance: wood oil. The principle is "one of the basic principles of who dirty who first decided to order" is also home, actually like a package of legislation, decorative ceiling, sticking plaster line like carpentry sense considered can be used as a small part of the main Chaigai itself and the water circuit transformation and not conflict. Sometimes they need cooperation and advance taking into account.